SOE15242 – Balcombe Road, Horley (Hatchgate, Wheatfield Way)

PROJECT: SOE15242

Location: Balcombe Road, Horley
(Hatchgate, Wheatfield Way)

Update: 29.04.2026

Works have now been completed in Hatchgate. Reinstatement is due to be finished this week, after which all barriers and remaining site equipment will be removed.

The team is currently working in Wheatfield Way under temporary traffic lights. This week is a preparation phase, focused mainly on identifying the condition and exact location of the existing gas main.

The team is expected to remain in Wheatfield Way for approximately five weeks to complete the full gas mains replacement under traffic management.

We thank residents and road users for their patience and cooperation while these essential works are carried out. 

WCB Utilities Ltd Project Balcombe Road, Horley (Hevers Avenue)

Update: 08.07.2025

Project completed.

Update: 17.06.2025

Hevers Avenue has been found to have extra main that needs replacing that wasn’t the original plan, further investigation work has proved this, the team will be looking to start Meadowcroft Close week commencing 30/06/2025. 

Update: 03.06.2025

Works are progressing well on this site at Hevers Avenue. We are doing some internal prep work on properties in Parkway.  We look to start digging on this road WC 09/06/2025.