SOE15424 – Battle Hill, Battle
PROJECT: SOE15424
Location: Battle Hill, Battle
Update: 23.09.2025
Project completed.
Update: 09.09.2025
01/09/25 saw our road closure on Battle Hill erected. This was proposed to be a 6 week duration.
I am proud to say that the team as off 09/09/25 have completed all 300m of gas mains replacement.
This is due to the team putting in extra hours and ensuring all work that could be completed in a works day was done.
The road will remain closed until Friday to allow for concrete curing and other reinstatement along with site clearing.