SOE14349 – Boundary Road, Carshalton

Update: 03.06.2025

PROJECT: SOE14349

Location: Boundary Road, Carshalton

Update: 03.06.2025

Project completed. 

Update: 20.05.2025

Team 1 have finished on Woodcote Avenue and have left the project, we will return at a later date to complete the rest of this project.

Team 2 have finished the works on Heathdene Road and Hawthorn Road, we have some reinstatement to sort on Heathdene Road but we are looking to complete this by Friday.

Update: 06.05.2025

Team 1 are making steady progress in Woodcote Avenue, we have encountered some riser work that needs to be investigated further. The team will then move into Hall Road and Heathdene Road.

Team 2 are currently working on Hawthorn Road, we will need to close Heathdene and Hawthorn at the same time, a diversion will be in place for both and access will be maintained as usual

Update: 22.04.2025

Team 1 have completed Dower Avenue and they are making steady progress in Woodcote Avenue, we have encountered some riser work that needs to be investigated further. The team will then move into Hall Road and Heathdene Road.

Team 2 have completed Boundary Road, this week Heathdene Road between Boundary Road and Park Hill Road will be completed and the team will finish in Hawthorn Road between Boundary Road to Park Hill Road.

WCB Utilities Ltd Project Boundary Road

Update: 08.04.2025

Team 1- Working in Woodcote Avenue Private section, we will be in Dower Avenue Week Commencing 31.03.25.

Team 2- W/C 21.04.25 the team will return from Easter time critical works to Heathdene road. 

Update: 21.03.2025

Team 1- Working in Woodcote Avenue Private section, we will be in Dower Avenue Week Commencing 31.03.25

Team 2- Working in Boundary Road works are progressing well we will be in Brambledown Road as of week commencing 31.03.25

Update: 04.03.2025

Team 1- Working in Woodcote Avenue. The Wood End and The Woodlands, Works are progressing well

Team 2- Working in Boundary Road works are progressing well

Update: 17.02.2025

We have 2 teams on this project.

Team 1 – working in Woodcote Avenue. The Wood End and The Woodlands, works are progressing well.

Team 2 – working in Boundary Road, we will be closing Brambledown Road on Monday, again works are progressing well.