Due to our team prep working last week, it has seen them be able to get a 100m push in Tibbets Close.
The team are expected here for another 2 weeks.
However, our closure on Tilford Gardens will be removed on the 4th of July.
Update: 17.06.2025
This week saw our team doing some prep and investigation work to then allow us to start replacing a section of metallic gas main to new PE pipe. A closure has been put in place to allow us to do our final connections and provide a back fed for the gas services.
This project will take place for approx. 4 weeks, and all closure and site content will be removed.