SOE15136 – Farleigh Road / Clovelly Avenue, Warlingham (Tithepit Shaw Lane)
PROJECT: SOE15136
Location: Farleigh Road / Clovelly Avenue, Warlingham
(Tithepit Shaw Lane)
Update: 16.11.2026
Last week, the team successfully completed the insertion works along Farleigh Road and into the junction with Crewes Lane, bringing the works on this road to completion.
This week, the team will move to Clovelly Avenue, where they will install approximately 130m of new water main and abandon the existing main, working from the junction with Westhall Road to outside property number 3.
Next week, the team will continue along Clovelly Avenue, installing a further 110m of new water main and abandoning the existing main, between outside properties 4 and 8.
Update: 29.10.2026
Last week, one team completed trial holes and preparatory works along the full length of Albert Road ahead of the gas main replacement. Meanwhile, a second team installed approximately 85 metres of new gas main on Farleigh Road, between properties 187 and 175.
This week, works will continue with one team replacing the existing gas main along the full length of Albert Road, while the second team progresses along Farleigh Road, installing new gas main from property 175 to property 161 and connecting to the existing PE main.
Farleigh Road is scheduled to reopen on 11 November 2026.
Update: 14.10.2026
Last week, the team abandoned the existing gas main on Farleigh Road, working from the junction with Crewes Lane down to property 188.
This week, the team will begin preparatory work and carry out trial holes on the final section of Farleigh Road, from property 188 down to property 161.
Next week, the team will complete the installation of the new gas main along this final section, from property 188 down to property 161.
Farleigh Road is scheduled to reopen on 4 November.
Update: 30.09.2026
Last week, the team completed the works on Alexandra Road. They also began works on Farleigh Road, carrying out live insertion works from the roundabout with Sunny Bank up to property 161.
This week, the team will remain on Farleigh Road, carrying out live insertion works from property 161 up to the junction with Crewes Lane. They will also abandon the existing main between properties 161 and 169.
Next week, the team will continue live insertion works up to property 221, while also completing the connection into Crewes Lane. They will abandon the existing main from property 189 up to the junction with Crewes Lane.
Planned road opening:
• Farleigh Road: Due to open on 4 November 2026
Update: 17.09.2026
Last week, we carried out approximately 160m of dead insertion works on Alexandra Road, starting from the junction with Chelsham Road.
This week, we are completing a further 140m of dead insertion works on Alexandra Road, progressing towards Greenhill Lane to complete the works on this road.
Next week, we plan to carry out approximately 250m of live insertion works on Farleigh Road, starting from the roundabout with Sunny Bank.
Alexandra Road is due to open on 02/10/26. Farleigh Road is due to close on 21/09/26 and open again on 30/10/26.