SOE5961 – High Street / Hookwood Park, Limpsfield (High Street)
PROJECT: SOE5961
Location: High Street / Hookwood Park, Limpsfield
(High Street)
Update: 16.11.2026
Last week, the team completed approximately 175m of new water main installation, working from White Heart Lodge to the junction with Hookwood Corner in Hookwood Park.
This week, the team will continue along High Street, installing a further 125m of new water main and abandoning the existing main, progressing up to the junction with Detilens Lane.
Next week, the team will return to Hookwood Park, where they will carry out live insertion works along approximately 150m of main, working from the junction with Hookwood Corner to outside property number 9.
Road Reopening Update
• High Street is currently scheduled to reopen on 21 November.
Update: 29.10.2026
Last week, the team carried out prep work and trial holes on the next section of the High Street.
This week, the team will insert and abandon the main form the junction with Sylvan Close up to White Hart Lodge.
Next week, the team will continue up the High Street, inserting and abandoning up to the junction with Hookwood Park.
High Street is due to reopen on 21/11/26.
Update: 14.10.2026
Last week, the team installed 120m of new gas main along High Street, between the junction with Westerham Road and the junction with Sylvan Close.
This week, work will move into Sylvan Close, where the team will replace the full 110m of gas main along the road. Work will also continue along High Street, with a further 150m of gas main being installed up to White Heart Lodge.
Next week, the team will abandon the existing main that was replaced during this week’s works.
Sylvan Close: Expected to reopen on 30 October.