SOE15113 – Hilltop Walk / Camp Road, Woldingham (Butler’s Dene Road)

PROJECT: SOE15113

Location: Hilltop Walk / Camp Road, Woldingham

(Butler’s Dene Road)

Update: 30.09.2026

Last week, the team completed the live insertion works on Hilltop Walk up to property 19.

This week, the team will remain on Hilltop Walk to complete the remaining insertion works up to property 50. They will then move on to the open-cut works to complete the works on this road.

Next week, the team will carry out live insertion works along the full length of Camp Road. At the same time, approximately 80 metres of new main will be laid along the Woldingham bridleway, starting from the junction with Hilltop Walk.

Planned road and bridleway openings:

• Hilltop Walk: Due to open on 12 October 2026
• Woldingham bridleway: Due to open on 26 October 2026
• Camp Road: Due to open on 6 November 2026  

WCB Utilities Ltd Project Butler’s Dene Road, Woldingham (Hilltop Walk)

Update: 17.09.2026

Last week, we successfully completed the Three Elm Lane project in Tonbridge.

This week, we are carrying out approximately 320m of live gas main insertion along the first two sections of Hilltop Walk. Approximately 120m of existing gas main will be abandoned.

Next week, we plan to abandon the remaining 200m of existing gas main on Hilltop Walk. Preparation works will also begin for the upcoming open-cut works on the final section of Hilltop Walk.

Hilltop Walk is due to be completely open on 12/10/26 to allow for reinstatement of the road.