SOE13195 – Monaveen Gardens, Molesey (Spurfield)
PROJECT: SOE13195
Location: Monaveen Gardens, Molesey
(Spurfield)
Update: 23.09.2025
We are currently working in Spurfield but we are having to pull away due to urgent works that are now taking priority week commencing 29/09/2025, letters will be sent again when we can return to finish these works.
Update: 26.08.2025
We will be starting this project again W/C 08/09/2025.
Update: 08.07.2025
Works are progressing well in Cherimoya Gardens and Monaveen Gardens, but it looks like we wont be completing all of this before the summer holidays start, which the team will need to come away and complete the summer holidays works, we will notify the residents when we plan to return to complete the rest of the works.
Update: 17.06.2025
Works are progressing well through Dundas Gardens and Kelvinbrook, we look to be in Cherimoya Gardens WC 23/06/2025.
Update: 03.06.2025
Works are progressing well through Dundas Gardens and Kelvinbrook, we look to be in Cherimoya Gardens WC 16/09/2025.
Update: 20.05.2025
Our WCB Utilities team are currently working their way through Kelvinbrook, this week we are looking to start in Dundas Gardens, we have had a change in how we complete this project plus the material in the ground is different which helps with progression.
Update: 06.05.2025
Our team working on Mole Abbey Gardens and this will be complete end of this week, we will then move round to Kevlinbrook and Dundas Gardens.
Update: 22.04.2025
Our team will start on Mole Abbey Gardens replacing approximately 200m of main, after our works will take place on Kelvinbrook and Dundas Gardens as we make our way around the housing estate.