SOE16070 – Rockshaw Road, Redhill

Update: 24.02.2025

PROJECT: SOE16070

Location: Rockshaw Road, Redhill

Works now engineering complete.

Update: 13.02.2025
Our WCB Utilities team have finished all engineering works this week and all works for Rockshaw Road are finished much earlier then expected, the team have managed to complete the full length of Rockshaw in just 6 weeks.

Our reinstatement should be completed by W/c 17th February and the road closure lifted.

Update: 30.01.2025
We are inserting on average 300m a week on the main road, our closure is currently at the 3t bridge and will have to remain in this location due to if there was a need for emergency vehicles out of hours. We estimate this project to be much shorter then anticipated and will be done and reinstated by W//c 17th February.

WCB Utilities Ltd Project Rockshaw Road, Redhill