SOE15688 – Seddon Road, Morden (Phipps Bridge Road)

PROJECT: SOE15688

Location: Seddon Road, Morden

(Phipps Bridge Road)

Update: 08.10.2025

Site complete.

Update: 23.09.2025

Last week our team had open cut 40m due to the amount of rust in the old existing gas main which was affecting pressures and meaning we could not insert in this.
This week the team are looking to complete all engineering works, next week will be a case of just reinstatement taking place. If this week the team need to dig in the c/w there will be full width reinstatement taking place as this road has recently been resurfaced.

Once these works are complete all gas works in this area are now complete with new PE gas Mains. 

WCB Utilities Ltd Project Seddon Road, Morden (Phipps Bridge Road)