SOE10957 – Farleigh Lane, Maidstone (Farleigh Lane / Glebe Lane)
PROJECT: SOE10957
Location: Farleigh Lane, Maidstone
Update: 08.10.2025
Site complete.
Update: 23.09.2025
Last week the team was continuing to work from Tonbridge Road down to Fraleigh Lane. This week the team will be working from O/s 40 Fraleigh Lane to J/w Glebe Lane, engineering works will take place all week however, the reinstatement will fall into W/c 29th.
Once this is all completed the closure will be removed and works will be completed.
Update: 09.09.2025
Our closure has been implemented on Farleigh Lane at the junction of Tonbridge Road. This will be in place here for a further 2 weeks while the team continue down Farleigh Lane down to Glebe Lane. Once this section has been completed, the closure will move down to the south section of Farleigh Lane meaning all access will then be off Tonbridge Road, there will be a signed diversion in place for this change, and the junction of glebe lane will be closed to allow us for our final collections. We are also colab working with another company to prevent a further closure happening.