SOE15095 – Homestead Road, Orpington (Ringwood Avenue)
PROJECT: SOE15095
Location: Homestead Road, Orpington
(Ringwood Avenue)
Update: 02.12.2025
Project complete.
Update: 19.11.2025
We have implemented an upgraded traffic management system involving three-way traffic signals. The works are scheduled for completion during the week commencing 24 November.
Update: 05.11.2025
Works have now started on Ringwood Avenue and will be carried out under give and take traffic management. We expect to be working in this area for approximately three weeks.
Update: 21.10.2025
Our WCB team are now working on our last section on Church Road and have now installed three way lights on Court Road junction with Church Road. Engineering is looking to be complete.
Once this section is complete we will be going into Ringwood Avenue, Runciman Close and Downs View Close.
Update: 08.10.2025
Works on Chelsfield Hill are progressing well and we have moved our closure location to the jucntion of Sevenoaks road. Access to Church Road and Worlds End Lane will be accessible via a diversion route. After Friday 10th we will be moving the closure point again to Church Road. This will make Chelsfield Hill accessible from Sevenoaks Road and Worlds End Lane.
Update: 23.09.2025
Rushmore Hill is now open and completed. We have now moved our closure onto Chelsfield Hill J/W Worlds End Lane.
We will be pushing 3 ways from the junction and work on Chelsfield Hill. Once this is completed, we will concentrate on Church road.
Update: 10.09.2025
We will be opening up Rushmore Hill on 15th September. We will still be working on site but we can complete the last section without a closure.
Once this section is completed, we will start works on Church Road/Chelsfield hill/Worlds End Lane.
Update: 26.08.2025
We will be opening Norsted Lane on Wednesday 27th and we have placed our hard closure at the A21 end of Rushmore Hill. Works are still progressing well.
Update: 12.08.2025
Works are progressing well on Rushmore Hill. We have closed the junction of Norsted Lane and we have requested an extension on Rushmore Hill until 15/09/2025.
Update: 29.07.2025
Works are progressing well on Rushmore Hill. We have started works on Hookwood Road and once completed we will continue on Rushmore hill.
Update: 16.07.2025
Works are progressing well on Rushmore Hill. Week Commencing 28th July we will be Starting in Hookwood Road and we will complete this during the school Summer holidays.
Update: 08.07.2025
Works have commenced again on Rushmore Hill. We are looking to complete 300m a week for the first couple of weeks and access is maintained to the Coolings Garden Centre via the diversion. We ask you to please not park your cars within our road closure and walk to the garden centre.
Update: 17.06.2025
Norsted Lane engineering works will be completed Friday 20th and then it will be reinstatement left to complete. The road closure will be in place whilst we do reinstatement and then we will move over to Stonehouse Lane and Road WC 16/06/2025. The work will then be completed under road closures.
Update: 03.06.2025
We are starting here with a closure on Norsted Lane on Wednesday 4th June for 2 weeks and we will move over to Stonehouse Lane and Road WC 16/06/2025. The work will then be completed under road closures.
Update: 20.05.2025
Our 2 teams on site are completing the engineering works Tuesday 20/05/2025, then site with be cleared over the weekend. We do need to return at a later date to complete a road crossing on The Meadway at the junction of Windsor drive.
Update: 06.05.2025
We have a team on this site currently working on the insertion. We will be adding another team to focus on the open cut from The Meadway – Oxenden Wood Road. We will then need to close Oxenden Wood Road at the junction of The Woodlands week commencing 19th May.
Update: 08.04.2025
We have put a new gas main in the whole length of The Meadway. We are still needing The Meadway closed as works aren’t yet complete and we have a new team joining this site on 14th April to complete the rest of the works to the junction of Oxenden Wood Road.
Update: 21.03.2025
Prep work is underway on The Meadway and progressing well. Closure has now moved and access is maintained from Windsor Drive up to Spring Gardens.
Update: 04.03.2025
Our WCB Utilities team are prepping work which is now underway on The Meadway and progressing well.
Update: 17.02.2025
We have now transferring the services over to the new main on Oxenden Wood Road. Once this is completed we will start open cutting a new main on The Meadway.
Update: 30.01.2025
Our have started and prep work is being undertaken on Oxenden Wood Road.
Update: 17.01.2025
Our works are due to commence 27/01/2025- this will entail us open cutting a new main on Oxenden Wood Road.
Update: 05.12.2024
We are currently working on Worlds End Lane between Oxenden Wood Road and Homestead Road. Works are progressing well and we will have the site cleared by 20th December.
We have a second team to start on The Hillside week commencing 09/12/2024.
Update: 21.11.2024
We are currently working on Worlds End Lane between Brimstone Close – Oxenden Wood Road. We are experiencing poor pressures due to the cold snap. This makes operations difficult and sometimes we are unable to complete.
Update: 06.11.2024
We are currently working on Worlds End Lane between Chelsfield Hill and Brimstone Close, a second team are working in Spring Gardens.
Update: 28.10.2024
We are currently working in Brimstone Close. Worlds End Lane will start 04/11/2024 with the first phase expected to last 10 days.
Update: 11.10.2024
We have completed an amount of main in Homestead Road, we will be moving onto Brimstone Close next week.