SOE17371 – Fauchons Lane, Maidstone
Update: 28.02.2025
PROJECT: SOE17371
Location: Fauchons Lane, Maidstone
Our WCB Utilities team has now fully completed this project and all barriers, and the closure was removed as of 26/02/2025.
Update: 24.02.2025
Works now engineering complete.
Update: 13.02.2025
Our WCB Utilities team returned to site this week, in which they prep worked getting out everything needed and doing some internal work on properties, so that W/c 17th they will be able to complete this roads replacement in a week only. This will see approximately 330m completed in just one week.
Update: 30.01.2025
We have had to put a hold on these works due to an emergency project that has resulted in our team needing to attend. We are aiming to return to this project week commencing 10th feb for 1-2 weeks to finish off what was left.
Update: 17.01.2025
We estimate for these works to be done w/c 7th February, currently we are looking to do 150m of insertion down Fauchons lane, reinstating as we go. So far, the project has gone smooth and have colab worked with others on the Ashford Road.