SOE15631 – Beldam Haw, Sevenoaks (Rushmore Hill)

PROJECT: SOE15631

Location: Beldam Haw, Sevenoaks

(Rushmore Hill)

Update: 17.03.2026

Works complete.

Update: 22.04.2025

We have a road closure on Rushmore Hill, we are working under a rolling road closure from the junction of Halstead Lane to Coolings Garden Centre.

In our first two weeks we have replaced over 400m of old metallic gas main and w/c 28.04 we aim to achieve a further 400m of replacement. Once we reach the entrance of the garden centre, we will be re opening the road for a period of time and returning at the beginning of July to finish our replacement scheme from the Garden centre to the A21. 

WCB Utilities Ltd Project Ellerton Road, Wimbledon (Drax Avenue)

Update: 05.12.2024

Our WCB Utilities team will be returning at a later date to complete rest of this project.

Update: 21.11.2024

Our have a connection to complete on The Meadows.  We will then be complete until next year’s Summer holidays.

Update: 06.11.2024

We have finished works on Otford Lane and site is clear.  We are currently working in The Meadows.

Update: 28.10.2024

We have completed Church Road and now have started in Otford Lane, where the first 300m of gas main have been inserted.  Works are expected to last another 2 weeks.

Update: 11.10.2024

We are one week away from finishing in Church Road.  Once this has been completed we will be moving onto The Meadows, week commencing 21/10/2024.  We will be working in Otford Lane with a road Closure.

Update: 25.09.2024

We have completed Beldam Haw, and have moved onto Station Road, this will be completed by next week. Once Station Road is complete we will move onto Church Road.