SOE15642 – Carters Road, Epsom
Update: 08.04.2025
PROJECT: SOE15642
Location: Carters Road, Epsom
Project complete.
Update: 21.03.2025
Our WCB Utilities team has now completed all works in Links Road and the closure has been removed. All barriers will have been removed, and site is clear. The team has now moved to Copse Edge Avenue in which the team are looking to complete this in a 3-week period should all plans go as thought.
Update: 28.02.2025
We have been doing a great job on this project and has seen them still exactly to schedule as originally planned. The team have now completed, Ashdown Road, Kingsdown Road and Longdown Road and are looking to complete the last remaining gas mains replacement on Links Road by W/c 10th. Our road closure will be lifted, and all works barriers, and outstanding holes will be backfilled and removed.