SOE20066 – Woodcote Lane, Purley (Rose Walk)
PROJECT: SOE20066
Location: Woodcote Lane, Purley
(Rose Walk)
Update: 16.11.2026
Last week, the team successfully installed approximately 130m of new water main and abandoned the existing main along Woodcote Lane, from Downside School to property number 7.
This week, the team will install approximately 30m of new water main and abandon the existing main at the top of Woodcote Lane. They will also complete the connection into Foxley Lane.
Next week, the team will continue along Woodcote Lane, installing a further 100m of new water main and abandoning the existing main, progressing from property number 7 towards Cumnor House School.
Traffic Management Update
The temporary traffic lights on Foxley Lane are currently scheduled to be removed on 22 November.
Update: 29.10.2026
Last week, the team installed new gas main along Woodcote Lane, progressing from the junction with Foxley Lane down to Cumnor House School for Girls.
Next week, the team will continue the installation works further along Woodcote Lane, bypassing the school and progressing from property 3 down to Cumnor House Nursery.
Update: 14.10.2026
Last week, the team installed 190m of new gas main along Farm Drive, from ‘Spindlewood’ to ‘Clifton’.
This week, the team will abandon the existing gas main that has been replaced on Farm Drive, completing the works on this road.
Next week, the team will move to Woodcote Lane, where they will install 215mof new gas main, starting at the junction with Foxley Lane and continuing to ‘Grey Timbers’.
Farm Drive is expected to open this week.
Update: 30.09.2026
Last week, the team completed the live insertion of the main on Promenade de Verdun, working from the junction with Farm Drive to complete the works on the road.
This week, the team will lay new main along the alleyway between Promenade de Verdun and Silver Lane. They will also begin preparatory works on Farm Drive.
Next week, the team will carry out live insertion works along the full length of Farm Drive.
Planned road openings:
• Promenade de Verdun: Due to open next week
• Farm Drive: Due to open on 12 October 2026
Update: 17.09.2026
Last week, we successfully completed the connection into Rose Walk. Live insertion works were also carried out on promenade de Verdun from the Cumnor House School for Girls to the junction with The South Border.
This week, we are carrying out live insertion works from the junction with The South Border. The connection into The South Border has also been completed.
Next week, we plan to carry out approximately 120m of gas main abandonment on promenade de Verdun.
Update: 01.09.2026
This week, the team will be working on Promenade de Verdun, completing a 200-meter live push from the junction with Rose Walk to the junction with The South Border.