SOE20067 – Furze Lane (Silver Lane) 

PROJECT: SOE20067

Location: Furze Lane

(Silver Lane)

Update: 19.08.2026

The team won’t be here this week as they are on annual leave.   

Update: 05.08.2026

Our WCB Utilities team laid approximately 135 meters of new main along Silver Lane last week, starting from the junction with Briar Hill.

This week, work will continue with a further 135 meters of new main being laid along Silver Lane.

Next week, the team will progress a further 180 meters along Silver Lane.