SOE5961 – High Street, Limpsfield (High Street)
PROJECT: SOE5961
Location: High Street, Limpsfield
(High Street)
Update: 14.10.2026
Last week, the team installed 120m of new gas main along High Street, between the junction with Westerham Road and the junction with Sylvan Close.
This week, work will move into Sylvan Close, where the team will replace the full 110m of gas main along the road. Work will also continue along High Street, with a further 150m of gas main being installed up to White Heart Lodge.
Next week, the team will abandon the existing main that was replaced during this week’s works.
Sylvan Close: Expected to reopen on 30 October.
High Street: Expected to reopen on 21 November.