SOE18007 – Highfield Road, Purley (Hillcrest Road)
PROJECT: SOE18007
Location: Highfield Road, Purley
(Hillcrest Road)
Update: 16.11.2026
Last week, the team successfully completed approximately 100m of open-cut works along Highfield Road, progressing up to property number 30.
This week, the team will carry out preparatory works ahead of the next phase of open-cut works, covering the section between properties 30 and 40.
Next week, the team will continue with the open-cut works, completing approximately 85m of work along Highfield Road, from property number 30 to property number 40.
Road Reopening Update
• Highfield Road is currently scheduled to reopen on 30 December.
Update: 29.10.2026
Last week, the team began open-cut works on Highfield Road, progressing from the junction with Plough Lane to outside property 12.
This week, the team will carry out preparatory works for a further 100 metres of open-cut excavation along Highfield Road, progressing towards property 30.
Next week, the team will complete the open-cut works prepared during this week.
Highfield Road is due to reopen on 30/12/26.
Update: 17.03.2026
Works complete.
Update: 10.02.2026
Works on Russell Hill are now in their final stages. However, we still need to complete a connection onto Plough Lane. As this work must be carried out during a school holiday period, we will need to return at a later date to complete it.
All other works are due to be finished by 23/02/2026.
Update: 27.01.2026
The one-way traffic system has now been implemented on Russell Hill.
To help accelerate the works, we are preparing to achieve approximately 200 metres per week where conditions allow. Progress has been impacted by unforeseen services, including the need to open-cut additional sections of main and replace extra lengths of main that were not identified in the original scope.
These additional works were necessary to ensure the integrity of the network and comply with required standards. We will continue to provide updates as the works progress.
Update: 14.01.2026
The one-way traffic system has now been implemented on Russell Hill.
To help accelerate the works, we are preparing to achieve approximately 200 metres per week where conditions allow. Progress has been impacted by unforeseen services, including the need to open-cut additional sections of main and replace extra lengths of main that were not identified in the original scope.
These additional works were necessary to ensure the integrity of the network and comply with required standards. We will continue to provide updates as the works progress.
Update: 17.12.2025
Delays have been experienced on Russell Hill due to low gas pressures, multiple-occupancy buildings, and the presence of additional gas mains that were not previously recorded. The site is currently being cleared in preparation for the Christmas shutdown. Works are scheduled to recommence on 2 January 2026, at which time the one-way road closure will be reinstated.
Update: 02.12.2025
Works on Russell Hill have been progressing well. A significant amount of preparation has been required before we are able to lay and connect the new gas main. Next week, we will begin our insertion works, which should allow the team to progress more quickly along the road. These works will continue into the New Year.
We have experienced issues with road users travelling the wrong way through the one-way system. Please can all drivers adhere to the traffic management in place to ensure the safety of our workforce, pedestrians, and other road users.
Update: 05.11.2025
Please be advised that works on Russell Hill are scheduled to commence on 10th November. During this period, Russell Hill will operate under a one-way system. Access will be via Russell Hill Road, with exit permitted onto Plough Lane only.
This project is compulsory and must be completed within a specified timeframe. We are aware that there are schools within the vicinity of the works, and they have been consulted accordingly.
To assist with traffic management, lorry movements will be restricted during peak school hours to help maintain the safe and efficient flow of traffic.