SOE9464 – Hillcroombe Road, Sutton (Hillcroome Road / Downside Road)
PROJECT: SOE9464
Location: Hillcroombe Road, Sutton
(Hillcroome Road / Downside Road)
Update; 17.03.2026
Works complete.
Update: 10.02.2026
Most of the works on Hillcroome Road have now been completed. We have a small section of open-cut excavation to finish at the junction of Mayfield Road.
We are also currently working on Upland Road and Downside Road. These works will be carried out under a road closure.
Update: 27.01.2026
Works have now commenced on Hillcroome Road, which is subject to a road closure. These works are expected to take approximately two weeks, after which we will progress to Upland Road, where a further closure will be in place.
We will then continue towards Downside Road, where the project will be completed.
Update: 14.01.2026
A road closure has been erected on Downside Road at the junction with Banstead Road. Approximately 75% of the works on Downside Road have now been completed.
To facilitate collaborative works with the water board, we now need to commence works on Hillcroome Road. These works will begin on Monday 19th January, starting at the junction with Mayfield Road and progressing towards Upland Road.
Update: 17.12.2025
Works on Farm Close have been completed, and site clearance is nearing completion. The works are scheduled to recommence in the area on Downside Road on 2 January 2026. The works will be undertaken with a closure in place at the junction of Banstead Road.
Update: 02.12.2025
Works have been completed on Willis Avenue and Prior Avenue. These sections were prioritised due to upcoming resurfacing works. We are now finalising the last section of Kayemoor Avenue, after which we will progress into Farm Close.
Update: 19.11.2025
Gas mains replacement works on Willis Avenue have commenced under a road closure at the junction with Banstead Road. We will then progress into Prior Avenue to accommodate planned resurfacing works scheduled for early December. Upon completion of these activities, we will continue into Kayemoor Avenue.
Update: 05.11.2025
We are returning to this project and will be starting works on Willis Avenue and Prior Avenue from 10th November.
Priority will be given to Prior Avenue, as the council are planning to resurface the carriageway.
We expect to be working on these roads for approximately 4 weeks, gradually progressing into Kayemoor Avenue as the project continues.
Update: 26.08.2025
Project complete.
Update: 08.07.2025
We have one more week left on Upland Road and the team will be leaving to complete another project.
Update: 17.06.2025
The team have finished in Chalgrove Road and have moved onto Upland Road where the road closure has moved and we will be here for an estimated 4 weeks.
Update: 03.06.2025
The team have finished in Chalgrove Road and have moved onto Upland Road where the road closure has moved and we will be here for an estimated 4 weeks.
Update: 20.05.2025
Our WCB Utilities team are progressing well and will be finishing in Chalgrove Road WC 02/06/2025, the next road due to be replaced is Upland Road full length, this will be completed under a road closure.
Update: 06.05.2025
We have moved the location of the road closure to the junction of Mayfield Road, we are continuing on The Ridgway and working our way round to Chalgrove Road.
Update: 22.04.2025
Our WCB Utilities team continue to decommission the main along The Ridgeway. This will be completed w/c 05.05.2025 and we will be completing a small section on Chalgrove Road. The next road will be Upland road where we have over 750m of old metallic gas main to replace.
Update: 08.04.2025
Our team will return to The Ridgway once they are back from their Easter critical work WC 21.04.25.
Update: 21.02.2025
We have already replaced Mayfield Road and we will be working in The Ridgway week commencing 24/03/2025.