Update: 08.10.2025

Site complete.

Update: 23.09.2025

W/c 8th saw our team arrive on site however, upon arrival the team had found that a majority of this road had already been replaced with new PE mains.
W/c 15th saw our team therefore do some more investigation work to determine what needs finishing and what is already done. Ther team therefore completed from J/w Upper Court Road to O/s 52.
W/c 22nd this week the team are looking to complete all the remaining replacement in this close once all engineering is complete w/c 29th the road will still have barriers in place to allow for reinstatement to take place once this is completed all barriers and other site content will be removed. 