SOE15656 – Blackland Meadows / Kings Mill Lane, Redhill (Mid Street)
PROJECT: SOE15656
Location: Blackland Meadows / Kings Mill Lane, Redhill
(Mid Street)
Update: 16.11.2026
Last week, the team successfully installed approximately 100m of new water main and abandoned the existing main along Blackland Meadows, between property numbers 26 and 6. This completed the works on this road.
This week, the team will move to Kings Mill Lane, where they plan to carry out dead insertion works and abandon approximately 300m of existing water main along the section past the aerodrome.
Next week, the team will continue working along Kings Mill Lane, carrying out dead insertion works and abandoning a further 135m of existing water main as they progress up the road.
Road Closure Update
Kings Mill Lane is currently scheduled to reopen on 23 March.
Update: 29.10.2026
Last week, the team completed the gas main insertion works along Parkwood Road and Blackland Meadows, progressing from the junction with Nutfield Road to property 6.
This week, the team will continue insertion works along Blackland Meadows, starting at property 6, progressing across to property 33 and then up to property 28.
Next week, the team will continue the insertion works back towards property 6 to complete the works along this road.
Parkwood Road and Blackland Meadows are scheduled to reopen on 23 November 2026.
Update: 14.10.2026
Last week, the team installed 220m of new gas main, starting at the junction with Mid Street and continuing up to ‘Hale Oaks’ on the Queens Court side of the road.
This week, the team will begin abandoning the existing gas main on both sides of the road, starting outside ‘Oak Tree House’.
Next week, the team will begin preparatory work in Blackland Meadows.
Mid Street: Expected to reopen on 20 October
Kings Cross Lane: Expected to reopen on 21 October
Update: 30.09.2026
Last week, the team had a top cutter on site to prepare for the open-cut works on Mid Street.
This week, the team will open-cut approximately 75 metres of main on Mid Street, working down to the junction with King’s Cross Lane to complete the works on this road. They will also complete the final connection into Ridge Green.
Next week, the team will move to King’s Cross Lane, where they will carry out live insertion works along approximately 220 metres of main, from the junction with Mid Street to the property known as ‘Hale Oaks’.
Planned road openings:
• Mid Street: Due to open on 20 October 2026
• King’s Cross Lane: Due to close next week and reopen on 21 October 2026
Update: 17.09.2026
Last week, we completed the abandonment of approximately 150m of existing gas main on mid Street, starting from the junction with The Avenue.
This week, we are carrying out approximately 1000m of live insertion, up to the junction of Ridge Green and completing the connection into Ridge Green.
Next week, preparation work will begin, using a top cutter, for the open-cut works on the final section of Mid Street.
North Station Approach is now open. The Avenue is due to open on 22/09/26. Mid Street is due to open on 20/10/26.
Update: 01.09.2026
Last week, the team continued to work on North Station Approach, where they dead inserted and completed service relays up to the junction with Trindles Road. The team also completed a 100-metre live push down Mid Street.
This week, the team will stay on Mid Street to complete 100m of abandonment.
Update: 19.08.2026
Last week, the team abandoned 180m of gas main along Mid Street, extending past the junction with Trindles Road.
This week, the team will install 150m of new gas main along Mid Street, continuing down to the junction with North Station Approach.
Next week, the team will abandon a further 85m of gas main along North Station Approach, extending up to the junction with Trindles Road.
Update: 05.08.2026
Our WCB Utilities team laid approximately 160 meters of new main along Mid Street last week.
This week, work will continue with a further 180 meters of new main being laid along Mid Street, progressing to the junction with Trindles Road and into the junction with Braes Mead.
Next week, the team will continue a further 150 meters along Mid Street.
Update: 08.07.2026
Over the past three weeks, the team has been carrying out gas mains replacement works on The Avenue. This week is expected to be the final week of engineering works, after which the reinstatement team will follow to restore the affected areas. In total, approximately 1,000 metres of new gas main will have been installed in just under four weeks.
From next week, the team will move to Crickets Hill for approximately one week to complete the majority of the planned works on this road. While access may be restricted at times, every effort will be made to minimise disruption and maintain access for residents wherever possible.
Following completion of works on Crickets Hill, the team will move to Mid Street for the next phase of the project. These works will take place throughout the summer holiday period and into September, beginning near the school before progressing back towards The Avenue.
We would like to thank residents and road users for their continued patience, understanding and cooperation while these essential works are carried out to help maintain a safe and reliable gas network.
Update: 19.06.2026
Over the past few weeks, the team has successfully completed the replacement of the gas mains in Braes Mead, Ridge Green, and Ridge Green Close. Last week, the team also completed all planned gas main replacement works on Holmesdale Road.
This week, the team has moved into The Avenue, where a road closure has been implemented for the next four weeks. During this period, the team aims to replace just under 1,000 metres of gas main.
Due to the presence of two gas mains within The Avenue, a full road closure is required to allow the works to be carried out safely and efficiently.
We would like to thank residents for their continued patience, understanding, and cooperation while these essential works are carried out to help maintain a safe and reliable gas network.
Update: 02.06.2026
Over the last couple of weeks, the team have been working inside Ridge Green and Ridge Green Close, looking at completing this road w.c 01/06.
The team will help with reinstatement next week and help clear all the site content to get this road cleared asap.
We apologise for the inconvenience caused by our works and will get all completed as soon as possible.