SOE15074 – Leesons Hill, Bromley (Highfield Rd, Southfield Rd, Petershams Drive)

PROJECT: SOE15074

Location: Leesons Hill, Bromley

(Highfield Rd, Southfield Rd, Petershams Drive)

Update: 14.05.2026

As of last week, the team has successfully completed all works on Highfield and Southfield. Reinstatement works have been carried out this week to enable the removal of all remaining site equipment and traffic management from both roads.

The team is scheduled to move to Petershams Drive during the week commencing 18 May, where works will be undertaken under a road closure. All affected residents will be notified in advance, and AWS updates will be issued accordingly.

We would like to thank residents for their continued patience and cooperation while these essential works are carried out. 

WCB Utilities Ltd Project Leesons Hill, Bromley

Update: 29.04.2026

Over the past couple of weeks, the team has been working in Highfield Road and has successfully replaced approximately 300 metres of gas mains.

This week and next week, the team will continue works to complete both Highfield Road and Southfield.

Once the engineering works are finished, reinstatement will follow closely behind, and all site equipment, barriers, and traffic management will be removed once the area is fully completed.

The team will then move into Petershams Drive during the week commencing 18 May, where works will be carried out under a road closure. All affected residents will be notified in advance, and the AWS updates will also be issued accordingly.

We thank everyone for their patience and cooperation while these essential works are carried out.