SOE10961 – Longdon Wood, Bromley (Forest Drive, Ebury Close, Beech Dell, Park Ave)

PROJECT: SOE10961

Location: Longdon Wood, Bromley

(Forest Drive, Ebury Close, Beech Dell, Park Ave)

Update: 14.05.2026

The team is currently continuing works on Forest Drive, progressing with the installation of the booster main. This week, the team is undertaking further preparation works to enable an additional 50m section to be completed during the week commencing 18 May.

A further connection onto Westerham Road will also be required to complete the project. As this section is located on the public highway, the team is currently awaiting the necessary council approvals before these works can proceed.

Once these works have been scheduled, affected residents will be notified in advance. 

WCB Utilities Ltd Project Longdon Wood, Keston Park

Update: 29.04.2026

We currently have two teams working on this project, operating in separate areas to complete the works as efficiently as possible.

Team One completed all works in Beech Dell last week. Reinstatement has now been finished, and the road has been fully cleared of all site equipment and traffic management.

This week, the team has moved into Ebury Close, where works will be completed before progressing to Park Avenue to finish the final section outside 1–5 Park Avenue.

Reinstatement works are following closely behind on all completed sections, and we anticipate that once engineering works are finished in each road, reinstatement will follow approximately 3–5 days later.

Team Two is continuing to work in Forest Drive, carrying out the required open-cut excavation works along this section. The team is making good progress and currently expects these works to be completed within the next 3–4 weeks.

We apologise for any inconvenience these works may cause. Once completed, all works within the estate will be finished.  

Update: 10.02.2026

Works are progressing well on Forest Drive, we are starting on Forest Ridge Monday 23rd February we will work our way towards Forest Drive.

Update: 27.01.2026

Works on Barnet Wood Road have been completed and site clearance is nearing completion.

Works have now commenced on Forest Drive and are expected to last for approximately three weeks, after which works will progress into Forest Ridge.

Update: 14.01.2026

Barnet Wood Road is currently closed at the junction with Oakley Road. Due to the location of the gas main, the engineering works have been split into two weeks to help maintain access for residents.

Access will be restricted between 08:30 and 16:30 while works are being undertaken.
Once the works on Barnet Wood Road have been completed, works will commence on Forest Drive.

Update: 17.12.2025

Park Avenue

Works are now complete, and site clearance is currently being undertaken.

Barnet Wood Road / Forest Drive / Forest Ridge

Works are scheduled to commence on Barnet Wood Road during the week commencing 2 January 2026, under a full road closure. The closure will be located at the junction with Oakley Road and is expected to remain in place for approximately two weeks. Upon completion of these works, activities will progress into Forest Drive and Forest Ridge.

The Glen

Works are now complete, and site clearance is currently being undertaken.

Update: 02.12.2025

Park Avenue

Works are progressing well on Park Avenue, and we have successfully inserted and abandoned over 200 metres of main to date. This week, we aim to be working outside No. 11, after which we will begin works on Elm Walk.

Holmwood Park Avenue

Works on Holmwood Park Avenue are expected to be completed this week. We are also carrying out preparation works in Pine Glade this week, which will continue into next week. This will allow us to make an early push on the next phase of the programme.

The Glen

We are due to start works on The Glen during the week commencing 8th December. This will take us up to the Christmas break, and the team will complete as much as possible before the shutdown
We will start from the Park Avenue end of the road and work our way towards Elm Walk.

Update: 19.11.2025

Works have recommenced on Holwood Park Avenue and are progressing well. Once these works are completed next week, we will proceed to commence works in Pine Glade.
An additional team will commence works on Park Avenue from Monday.

Update: 31.10.2025

Please be advised that our operatives have been called away to support a high-profile project. As a result, they will be unavailable for their usual duties until the completion of this activity.
They are expected to return and resume normal work activities week commencing 10th November.
We appreciate everyone’s understanding and cooperation during this period.

Update: 08.10.2025

Our team have replaced the gas main in Ninhams Wood, they have now replaced half of the main in Longdon Wood and will continue to replace the opposite side before moving into Beech Dell and Holwood Park Avenue.

The team are making good progress in the roads and will be working in the estate on a variety of roads until March.