SOE15448 – Main Road, Queenborough

Update: 06.11.2024

PROJECT: SOE15448

Location: Main Road, Queenborough

Our WCB Utilities project at Main Road is now complete.

Update: 11.10.2024
We are still progressing along Main Road, these works have been very difficult, and a lot of investigation works have been needed to be completed however, the team are progressing aiming to complete these works by the end of October. We have added more labour onto this project, to try and speed up production and get the road open as quickly as possible.

SOE15448 - Main Road Queenborough

Update: 25.09.2024
We are still progressing along Main Road. These works have been very difficult and a lot of investigation works have been needed to be completed. However, the team are progressing, aiming to complete another 100m towards the dual carriageway. The phase of the closure will be changing on 25.09.24.

Update: 12.09.2024
Our team have had to do some more investigation works due to finding that the gas mains doesn’t  do essentially what our gas maps had shown us. Our team will still be progressing down the road aiming to complete another 100m section within the next two weeks, reinstating as they go to reduce the impact of our closure on residents in the area.