SOE5427 – Oare Road, Faversham
Update: 12.09.2024
PROJECT: SOE5427
Location: Oare Road, Faversham
Our WCB utilities team have completed this project.
Update: 29.08.2024
We have managed to complete the section of gas mains replacement that was on the main road to get it into the school grounds – The school will need replanning to due to discovering it had 5 gas meters instead of the anticipated 1 meter – Meaning next time we arrive, the works will be inside the school and a road closure wont be needed.
Update: 15.08.2024
We will be installing a road closure for the last two weeks of the summer holidays so we can complete the Davington schools feed onto the new gas main installed last year. This gas main has to be open trenched from the main to the meter, which is why a road closure in required to complete these works.