SOE15129 – Pinewood Road, Bromley

Update: 21.03.2025

PROJECT: SOE15129

Location: Pinewood Road, Bromley

Our WCB Utilities team have now completed works.

Update: 04.03.2025
We are currently working in Pinewood Road and Cromwell Avenue, we should be finished W/C 10/03/2025.

Update: 17.02.2025
We are currently working in Pinewood Road and Cromwell Avenue, we should be finished W/C 10/03/2025.

Update: 30.01.2025
The closure on Mead way has been cancelled due to a clash in traffic management that is out of our control, these works will be replanned at a later date.

Update: 17.01.2025
We are currently working on Sandford Road, works are being help up due to the gas main being under trees so we are having to open cut a new main.

We have a second team working on Pickhurst Park and Meadway, a closure will be erected on Monday/Tuesday depending on the works happening on Hayes Lane

Update: 05.12.2024
We are currently working in Cromwell Avenue/ Cromwell Close.  Works are progressing well and working our way towards Sandford Road.

We have a second team working on Stone Road and Cameron Road – this will not affect the buses.

SOE15129 South Hill Road, Bromley

Update: 21.11.2024
We are currently working in Cromwell Avenue/ Cromwell Close.  Works are progressing well and we are working our way towards Sandford Road.

Update: 06.11.2024
We are currently working in Langdon Road- Where we have encountered engineering problems and has delayed works  and Durham Avenue engineering will be completed end of this week then will be a case of reinstatement and site clearance.

Update: 11.10.2024
We have found extra mains that need to be replaced on Durham Road, however this shouldn’t cause much of a delay.  We are also starting in Langdon road as of next week.

Update: 12.09.2024
We are currently working in Durham Avenue, from Monday we will be in Durham Road with this junction closed for 2 weeks.

Update: 29.08.2024
This week we have inserted up to junction of Durham Avenue and will be clearing site to then start work in Druids Way.

Update: 15.08.2024
Week commencing 12.08.2024 our team will be getting up to Highfield Junior School and the week after we are on target to Durham Avenue.