SOE20066 – Promenade de Verdun / Farm Drive, Purley (Rose Walk)
PROJECT: SOE20066
Location: Promenade de Verdun / Farm Drive, Purley
(Rose Walk)
Update: 30.09.2026
Last week, the team completed the live insertion of the main on Promenade de Verdun, working from the junction with Farm Drive to complete the works on the road.
This week, the team will lay new main along the alleyway between Promenade de Verdun and Silver Lane. They will also begin preparatory works on Farm Drive.
Next week, the team will carry out live insertion works along the full length of Farm Drive.
Planned road openings:
• Promenade de Verdun: Due to open next week
• Farm Drive: Due to open on 12 October 2026
Update: 17.09.2026
Last week, we successfully completed the connection into Rose Walk. Live insertion works were also carried out on promenade de Verdun from the Cumnor House School for Girls to the junction with The South Border.
This week, we are carrying out live insertion works from the junction with The South Border. The connection into The South Border has also been completed.
In addition, two gas services have been completed on Galpin’s Road.
Next week, we plan to carry out approximately 120m of gas main abandonment on promenade de Verdun.
Update: 01.09.2026
This week, the team will be working on Promenade de Verdun, completing a 200-meter live push from the junction with Rose Walk to the junction with The South Border.