SOE20066 – Rose Walk, Purley (Promenade de Verdun)

PROJECT: SOE20066

Location: Rose Walk, Purley

(Promenade de Verdun)

Update: 17.09.2026

Last week, we successfully completed the connection into Rose Walk. Live insertion works were also carried out on promenade de Verdun from the Cumnor House School for Girls to the junction with The South Border.

This week, we are carrying out live insertion works from the junction with The South Border. The connection into The South Border has also been completed.

In addition, two gas services have been completed on Galpin’s Road.

Next week, we plan to carry out approximately 120m of gas main abandonment on promenade de Verdun.  

WCB Utilities Ltd Project Rose Walk (Promenade de Verdun), Purley

Update: 01.09.2026

This week, the team will be working on Promenade de Verdun, completing a 200-meter live push from the junction with Rose Walk to the junction with The South Border.