SOE17957 – The Ridge, Purley (Farm Lane)
PROJECT: SOE17957
Location: The Ridge, Purley
(Farm Lane)
Update: 30.09.2026
Last week, the team completed the works on Farm Drive.
This week, the team will move to The Ridge, where they will carry out dead insertion works from the junction with Farm Lane up to the junction with Linden Way.
Next week, the team will continue along The Ridge, carrying out insertion works from Linden Way up to property 16.
Planned road openings:
• Farm Lane: Due to open on 8 October 2026
• The Ridge: Due to open on 27 October 2026
Update: 17.09.2026
Last week, we completed approximately 90m of gas main insertion on Green Lane, progressing towards Farm Lane, leaving approximately 20m remaining.
This week, we are completing the remaining insertion works on Green Lane. We are also carrying out approximately 250m of gas main insertion on Farm Lane, covering the full length of the road from the junction of Foxley Lane up to the junction of The Ridge.
Next week, we plan to carry out approximately 170m of dead insertion works, starting from the junction with Farm Lane and progressing towards Purley Cricket Club.
Green Lane is due to open 22/09 /26 and Farm Lane is due to open on 08/10/26.