SOE18731 – Watling Street / Hever Court Road, Gravesend
PROJECT: SOE18731
Location: Watling Street / Hever Court Road, Gravesend
Update: 16.11.2026
Last week, the team successfully installed approximately 100m of new water main and abandoned the existing main, working from property number 1 on Watling Street to property number 31 on Hever Court Road. They also completed the connection into Singlewell Road.
This week, the team will continue along Hever Court Road, installing a further 100m of new water main, progressing from property number 31 to the junction with Westfield Close.
Next week, the team will install and abandon a further 140m of water main along Hever Court Road, working from the junction with Westfield Close to outside property number 65.
Road Reopening Update
• Hever Court Road is currently scheduled to reopen on 4 December.
Update: 29.10.2026
Last week, the team completed the gas main insertion works on Watling Street, live inserting from property 33 to finish the works on this road.
This week, the team will abandon the existing gas main along the section inserted last week. They will also continue insertion works on Hever Court Road and complete the connection at the junction with Singlewell Road.
Next week, the team will continue along Hever Court Road, installing a further 85 metres of new gas main.
Watling Street is due to reopen on 09/11. Singlewell Road is due to open on 06/11. Hever Court Road is due to reopen on 24/11.
Update: 14.10.2026
Last week, the team completed works on Old Watling Street, making the final connection into Golf Links Avenue. They then moved into Watling Street, installing new gas main from the junction with Golf Links Avenue to property 27.
This week, work will continue along Watling Street, with the team installing a further 140m of new gas main and making the connection into the footpath.
Next week, the team will continue installing the new gas main along Watling Street and begin preparatory works for the open-cut section into the footpath.
Old Watling Street: Expected to reopen on 16/10.
Watling Street: Expected to reopen on 06/11.
Update: 30.09.2026
Last week, the team carried out preparatory works for the upcoming works on Old Watling Street.
This week, the team will begin live insertion works from the junction with Golf Links Avenue to the property known as ‘Moorings’. They will also abandon approximately 100 metres of existing main.
Next week, the team will complete the works on Old Watling Street, including the connection into Golf Links Avenue. They will then begin live insertion works on Watling Street from the junction with Golf Links Avenue.
Planned road openings:
• Wrotham Road: Due to open on 2 October 2026
• Old Watling Street: Due to open on 16 October 2026
• Watling Street: Due to open on 26 October 2026
Update: 17.09.2026
This week, there is an installation of approximately 120m of new gas main on Wrotham Road, running from the junction with Chalky Bank down to the bottom of the cul-de-sac.
Next week, approximately 180m of open-cut gas main installation will take place from the junction with Golfs Link Avenue up to Casa Lila.
Wrotham Road is forecast to be closed until 02/10/26. Watling Street is due to close on 28/09/26 and due to reopen on 26/10/26.