SOE5344 – Westfield Avenue, Croydon
Update: 06.11.2024
PROJECT: SOE5344
Location: Westfield Avenue, Croydon
Our WCB Utilities works have been fully completed on Copthorne Rise; we currently have two-way traffic lights on Rectory Park, lights are manually controlled 7am-7pm to help with traffic flow. These will be in place until the 25th of November, In which will then see us jump back into Hyde Road for 3 weeks.
Update: 28.10.2014
Our works have been fully completed on Copthorne Rise; we currently have two-way traffic lights on Mitchley Avenue. These will be in place until the 18th of November. In which will then see us jump back into Hyde Road for 2-3 weeks.
Court hill is going to be reopened under give and take however, our muck bay will remain in this area.
Update: 11.10.2024
Our team have completed Westfield Avenue and will progress down onto Copthorne Rise week commencing 14th October, which will then see us go out onto Mitchley Avenue under two-way lights until 18th November. Currently you will see our reinstatement team on site backfilling and ensuring Westfield Avenue is clear and accessible.
Court hill will remain closed for all our works until the end of November.
Update: 25.09.2024
Our closure is due to kick in 26.09.24 on Westfield Avenue and Court Hill. Our team has smashed 400m in the first week and aiming to complete another 300m again next week.
We will continue Copthorne Rise and then lead out to Mitchley Avenue under traffic lights with side road closures.