SOE9315 – Wolfs Row, Limpsfield (Wolfs Road)

PROJECT: SOE9315

Location: Wolfs Row, Limpsfield

(Wolfs Road)

Update: 14.10.2026

Last week, the team installed 85m of new gas main along Wolfs Row, from property 6 to Heath Cottage, working on the side opposite the houses.

This week, work will move to the side of the road nearest the houses. The team will install a further 160m of gas main, completing the connection into Westerham Road and continuing towards Wolfe House.

Next week, the team will install a further 100m of gas main from Heath Cottage. This work will connect the two gas mains together and tie into the existing PE main just beyond Wolfe House.

Westerham Road: Expected to open on 18 October.
Wolfs Row: Expected to open on 5 November.  

WCB Utilities Ltd Project Wolfs Row, Limpsfield (Wolfs Road)