SOE6852 – Woodhyrst Gardens, Kenley (Croftleigh Ave, Reedham Park Ave, Cullesdown Rd)
PROJECT: SOE6852
Location: Woodhyrst Gardens, Kenley
(Croftleigh Ave, Reedham Park Ave, Cullesdown Rd)
Update: 14.05.2026
Reinstatement works have now been completed on Croftleigh Avenue, and this phase of works has been successfully cleared.
Over the coming weeks, the team is scheduled to begin works on Cullesden Road under a road closure, starting from Firs Road. Every effort will be made to complete the works as quickly and safely as possible.
Update: 29.04.2026
Over the past couple of weeks, the team has completed all works in Langham Dene, and the road has now been fully cleared.
Last week and this week, the team also completed all engineering works in Croftleigh Avenue and Reedham Park Avenue. This means that all services on these roads are now supplied by the new plastic mains.
Reinstatement works will take place next week, and we aim to have both roads fully cleared of all site equipment and traffic management by 8 May.
The team will then be finished in this area for a couple of weeks before returning to Cullesdown Road, where works will be carried out under a road closure. Advance warning and notification letters will be sent out over the next few weeks to ensure all residents are informed of the upcoming works on the main road.
We would like to thank everyone for their patience and cooperation in allowing us to complete these essential works, and we apologise for any inconvenience caused during the project.
Update: 01.04.2026
Last week, the team completed all final engineering works in Highland Road.
This week, the team has moved into Langham Park, where they aim to complete all works within the next two weeks.
Meanwhile, reinstatement works in Highland Road are taking place this week, and the site will begin to be cleared of equipment and traffic management.
We thank residents and road users for their continued patience and cooperation while these works are completed.
Update: 17.03.2026
Last week the team completed all works in Woodhyrst Gardens. This week the team has moved into Highland Road, where they aim to complete the insertion of all new gas mains during the week.
The abandonment works will then be completed over the following two weeks.
This programme means the team expects to move into Langham Dene during the week commencing 30 March.
Our reinstatement team will follow closely behind to ensure that completed sections are restored promptly and kept as close as possible to the current working area.
We appreciate the cooperation of residents in the area while these essential works are carried out.