SOE15136 – Tithepit Shaw Lane, Warlingham (Albert Road, Alexander Road, Chelsham Road)

WCB Utilities Ltd Project Tithepit Shaw Lane, Warlingham (Harrow Gardens, Harrow Road, Chelsham Road)

PROJECT: SOE15136 Location: Tithepit Shaw Lane, Warlingham (Albert Road, Alexander Road, Chelsham Road) Update: 08.07.2026 Over the past two weeks, the team has completed gas mains replacement works around the green at the junction of Chelsham Road and Chelsham Common. This week, the team is aiming to install approximately 500 metres of new gas main, SOE15136 – Tithepit Shaw Lane, Warlingham (Albert Road, Alexander Road, Chelsham Road)

SOE15113 – Butlers Dene Road, Woldingham (Butlers Dene Road / Slines Oak Road)

WCB Utilities Ltd Project Butlers Dene Road, Woldingham (Butlers Dene Road)

PROJECT: SOE15113 Location: Butlers Dene Road, Woldingham (Butlers Dene Road / Slines Oak Road) Update: 08.07.2026 Over the past two weeks, the team has been carrying out gas mains replacement works on Butlers Dene Road and Slines Oak Road. Works on Butlers Dene Road have now been successfully completed, and the team is continuing to SOE15113 – Butlers Dene Road, Woldingham (Butlers Dene Road / Slines Oak Road)

SOE13474 – Woodcote Valley Road, Purley (Purley Knoll Purley Rise)

WCB Utilities Ltd Project Woodcote Valley Road, Purley (Hill Road, Box Ridge Avenue, Purley Rise)

PROJECT: SOE13474 Location: Woodcote Valley Road, Purley (Hill Road, Box Ridge Avenue, Purley Rise) Update: 08.07.2026 Over the past couple of weeks, the team has been carrying out works on Purley Rise. The road closure has now been removed, and the team is aiming to complete the remaining works by the end of this week. SOE13474 – Woodcote Valley Road, Purley (Purley Knoll Purley Rise)

SOE12417 – Parklawn Avenue, Epsom (Parklawn Avenue, Eastdene Avenue)

WCB Utilities Ltd Project Parklawn Avenue, Epsom (Parklawn Avenue, Eastdene Avenue)

PROJECT: SOE12417 Location: Parklawn Avenue, Epsom (Parklawn Avenue, Eastdene Avenue) Update: 08.07.2026 Last week, the team successfully completed all planned works, with reinstatement carried out shortly afterwards. The site has now been fully cleared and all traffic management removed. One remaining service connection was completed following the main programme of works. With this now finished, SOE12417 – Parklawn Avenue, Epsom (Parklawn Avenue, Eastdene Avenue)

SOE18369 – Melfort Road, Thorton Heath (Carew Rd, Brook Rd, Boswell)

WCB Utilities Ltd Project Melfort Road, Thorton Heath

PROJECT: SOE18369 Location: Melfort Road, Thornton Heath (Carew Rd, Brook Rd, Boswell) Update: 08.07.2026 Project complete. Update: 19.06.2026 Last week, the team successfully completed all planned works on Woodcote Avenue, enabling the full 125 metres of gas main to be replaced within a single week. This week, the team has moved into Penshurst Road, where SOE18369 – Melfort Road, Thorton Heath (Carew Rd, Brook Rd, Boswell)

SOE15074 – Leesons Hill, Bromley (Petershams Drive)

WCB Utilities Ltd Project Leesons Hill, Bromley

PROJECT: SOE15074 Location: Leesons Hill, Bromley (Petershams Drive) Update: 19.06.2026 Project complete. Update: 02.06.2026 As of last week, the team have now completed all works in Petershams drive completing around 200m of mains replacement. This week will see the reinstatement team working on iste to ensure the road is back to its original site. Once SOE15074 – Leesons Hill, Bromley (Petershams Drive)

SOE14332 – Westhumble Street, Dorking (Pilgirms Way, Camilla Drive, Westhumble Street)

WCB Utilities Ltd Project Westhumble Street, Dorking

PROJECT: SOE14332 Location: Westhumble Street (Pilgirms Way, Camilla Drive, Westhumble Street) Update: 14.05.2026 Project complete. Update: 29.04.2026 Over the past few weeks, the team has completed all essential gas mains replacement works in Pilgrims Way. Reinstatement is now nearly complete, and the road will soon be fully cleared of all site equipment and traffic management. SOE14332 – Westhumble Street, Dorking (Pilgirms Way, Camilla Drive, Westhumble Street)

SOE6852 – Woodhyrst Gardens, Kenley (Cullesdown Rd)

WCB Utilities Ltd Project Woodhyrst Gardens, Kenley

PROJECT: SOE6852 Location: Woodhyrst Gardens, Kenley (Cullesdown Rd) Update: 08.07.2026 Over the past few weeks, the team has successfully completed more than 500 metres of 180mm gas main replacement, from the junction with Firs Road to Langham Dene. This week, the remaining service connections and tie-in to the existing gas main will be completed. Reinstatement SOE6852 – Woodhyrst Gardens, Kenley (Cullesdown Rd)

SOE7295 – Calder Road, Maidstone (Moncktons Lane / Sandling Road)

WCB Utilities Ltd Project Calder Road, Maidstone (Moncktons Lane)

PROJECT: SOE7295 Location: Calder Road, Maidstone (Moncktons Lane / Sandling Road) Update: 17.03.2026 Works complete. Update: 10.02.2026 Works on Moncktons Lane are now in their final week of engineering. This will be followed by reinstatement works and site clearance.  Update: 27.01.2026 Works have commenced on Moncktons Lane at the junction with Sandling Road under temporary SOE7295 – Calder Road, Maidstone (Moncktons Lane / Sandling Road)

SOE13449 – London Road, Uckfield (Snatts Road / Rocks Road)

WCB Utilities Ltd Project London Road, Uckfield (Cooper Green Road)

PROJECT: SOE13449 Location: london Road, Uckfield (Snatts Road / Rocks Road) Update: 17.03.2026 Works now conplete. Update: 24.02.2026 All works scheduled during the half-term period on Rocks Road have now been successfully completed. The road closure has now moved to the junction of Snatts Road, where it will remain in place for approximately the next SOE13449 – London Road, Uckfield (Snatts Road / Rocks Road)